Construction Update Brattleboro-Hinsdale Bridge – March 21, 2024
Work has continued on the cap for Pier 1 with the rebar being flown into place and tied atop the stem. Form work for the cap will be completed, bearing seats fully constructed, detail work finished, and everything fully adjusted to match plan location and elevation prior to the scheduled concrete placement next Tuesday.
Additional crews may begin work on the drainage installation required in the Barrows and Fisher yard late next week.