Construction Update Brattleboro-Hinsdale Bridge Dec 21, 2023
The construction of the temporary shoring tower between Piers 1 and 2 has been completed. The contractor will begin to advance structural steel over Pier 2 and to the shoring towers over the coming weeks. Additional measures to excavate were found to be required in the cofferdam prior to the placement of the concrete tremie seal and those measures were completed this week. The placement of concrete was rescheduled for today. The de-watering and subsequent operations of cutting piles and placing rebar cages have been rescheduled with the de-watering slated to begin middle/end of next week.