I-91 Brattleboro Bridge Replacement Project Update: March 7 -14
One-Way Traffic: This Saturday, March 7, we need to make a major concrete placement adjacent to Route Consequently, traffic on Vermont Route 30 within the work zone will be reduced to one-way beginning at 5:30 AM, and continuing to approximately 5:30 PM. Flaggers will be present to control traffic.
One-Way Traffic: The completion of the realignment or Route 30 is tentatively scheduled for completion on Monday, March 9. Traffic on Route 30 will be one-way during the day on Monday, as workers repaint the road. This work is weather dependent, so may need to be rescheduled.