Construction Update Brattleboro-Hinsdale Bridge – July 25, 2024

Formwork for sidewalks and rail copings is still being installed on the bridge deck. The installation of rebar for the bridge deck and the approach slab on the VT abutment will be completed this week. Multiple concrete placements are scheduled for next week for the bridge deck as well as the sidewalks and rail copings.

Paving of NH 119 finished earlier this week. Crews are scheduled to finish guardrail installation by the end of this week. Installation of asphalt curb and the application of pavement markings are scheduled for next week and the traffic pattern will remain as configured through these operations.


Construction Update Brattleboro-Hinsdale Bridge – July 19, 2024

Formwork for sidewalks and rail copings is still being installed on the bridge deck. Concrete is being placed today into a portion of those forms, and that work will continue. Placing concrete for another deck section is scheduled for July 24th.

Additional rebar to complete the bridge deck had to be ordered, and installation of that should be finished next week.

The subgrade for the approach slab at the Vermont abutment has been graded in preparation for building forms and installing rebar next week.


Construction Update Brattleboro-Hinsdale Bridge – July 12, 2024

Overhang formwork for the bridge deck and welding the girders to the VT abutment bridge shoes has been completed.

Crews are continuing to install stainless steel rebar for the bridge deck, and should complete that next week.

Conduit and hanger supports are being installed along the underside of the bridge this week, and should be completed early next week.


Construction Update Brattleboro-Hinsdale Bridge – July 3, 2024

Superstructure work continues to advance toward Vermont as the contractor continues formwork for overhangs. Shear stud placement and grouting have been completed and rebar installation will continue in earnest beginning on Monday, July 8th after the holiday. Dewatering and treatment tanks that have been awaiting removal have been tentatively scheduled to be cleaned and taken away sometime next week.


Construction Update Brattleboro-Hinsdale Bridge Update June 27, 2024

Work continues to progress toward the Vermont abutment on the remaining overhang formwork, placing shear studs into girders, grouting deck panels, and placing rebar. Grouting of deck panels in Vermont will take place on Monday, July 1st, with the concrete delivered to a pump truck located beneath the bridge in the Barrows & Fisher’s property.


Construction Update Brattleboro-Hinsdale Bridge – June 20, 2024

Increased construction traffic is anticipated adjacent to the work zone on Vermont Route 142 while the large crane is disassembled. Motorists should remain vigilant.

Due to current work on New Hampshire Route 119 associated with the project, the eastbound lane shift on NH 119 shortly after traveling over the twin bridges remains active. Signs and barrels are in place to assist motorists through the work zone.


Construction Update Brattleboro-Hinsdale Bridge – May 30, 2024

Last week’s operations of installing deck panels, forms for drainage scuppers within the deck, and brackets and forms for overhangs continue to progress westerly to reach the Vermont abutment. Tensioning of the bolts on cross-braces and steel diaphragms is being finalized. Cleaning and removal of the components of the water treatment system used at Pier 1 remains on hold.


Construction Update Brattleboro-Hinsdale Bridge – May 23, 2024

Crews continue to install deck panels, forms for drainage scuppers within the deck, and brackets and forms for overhangs as they progress westerly to reach the Vermont abutment. Welding the shear studs to the beams will also advance into Vermont next week. Tensioning of the bolts on the recently erected structural steel will be substantially complete this week. Cleaning and removal of the components of the water treatment system used at Pier 1 is on hold.


Construction Update Brattleboro-Hinsdale Bridge May 16, 2024

No traffic impacts are anticipated on Vermont Route 142 next week, however the work zone remains active and motorists should watch for construction vehicles entering and exiting the work site.

Due to current work on New Hampshire Route 119 associated with the project, vehicles traveling eastbound into New Hampshire from Vermont should expect a newly line-striped lane shift on NH 119 shortly after traveling over the twin bridges. Signs and barrels are in place to assist motorists through the work zone.


Construction Update Brattleboro-Hinsdale Bridge – April 25, 2024

The northbound shoulder will continue to be closed all week long and motorists are advised to watch for vehicles entering and exiting the construction site.

Delivery of steel to the abutment site on Vermont Route 142 is currently scheduled for Monday, April 29th, and Wednesday, May 1st. The delivery route is planned to provide direct access from the south along VT 142 from Massachusetts Route 10. Flaggers and Uniformed Traffic Officers will be available to assist with the delivery, however it is not anticipated to require a lane closure. When the steel is ready to be moved from the truck to the bridge, a brief hold of all traffic on VT 142 will be required.


Construction Update Brattleboro-Hinsdale Bridge – April 18, 2024

One way alternating traffic patterns with flaggers will be implemented on Vermont Route 142 adjacent to the construction site on Monday and Tuesday next week. The northbound shoulder will be closed all week long and motorists are advised to watch for vehicles entering and exiting the construction site.

Delivery of steel to the abutment site on VT 142 is currently scheduled for Wednesday, April 24th, Monday, April 29th, and Wednesday, May 1st. The delivery route is planned to provide direct access from the south along VT 142 from Massachusetts Route 10. Flaggers and Uniformed Traffic Officers will be available to assist with the delivery, however it is not anticipated to require a lane closure. When the steel is ready to be moved from the truck to the bridge, a brief hold of all traffic on VT 142 will be required.


Closure Reminder: Brattleboro-Hinsdale Bridge Project

A short duration closure (approximately 15 minutes) of VT/NH 119 can be expected today April 10th, tomorrow April 11th, Monday April 15th, and Wednesday April 17th at 11:00 a.m. for structural steel deliveries.

The delivery route of the structural steel to the Barrows and Fisher yard where the Pier 1 site is located will be along New Hampshire and Vermont Route 119 to Depot Street. This impact will include a short duration closure (approximately 15 minutes) of the twin bridges beginning at the intersection of Bridge Street to Canal Street, Main Street, and Vermont Route 142. Uniformed Traffic Officers will be located at the intersection’s entrance to Bridge Street during the closure period.


Construction Update Brattleboro-Hinsdale Bridge – April 3, 2024

Delivery of steel girders to Pier 1 is scheduled for Tuesday through Thursday, April 9th, 10th, and 11th, and Monday, April 15th.

The delivery route will be along New Hampshire and Vermont Route 119 to Depot Street. This impact will include a short duration closure (approximately 15 minutes) of the twin bridges beginning at the intersection of Bridge Street to Canal Street, Main Street, and Vermont Route 142. Uniformed Traffic Officers will be located at the intersection’s entrance to Bridge Street during the closure period. All deliveries are tentatively set for 1:00 p.m. to accommodate the train schedule.


Construction Update Brattleboro-Hinsdale Bridge – March 28, 2024

The contractor’s crews have been accessing the Vermont Abutment off of Vermont Route 142 and will continue to access this location next week. No traffic impacts are anticipated, but motorists are advised to watch for vehicles, including concrete trucks, entering and exiting the construction site.

Delivery of steel girders to Pier 1 is scheduled for Tuesday through Thursday, April 9th, 10th, and 11th, and Monday, April 15th.


Construction Update Brattleboro-Hinsdale Bridge – March 21, 2024

Work has continued on the cap for Pier 1 with the rebar being flown into place and tied atop the stem. Form work for the cap will be completed, bearing seats fully constructed, detail work finished, and everything fully adjusted to match plan location and elevation prior to the scheduled concrete placement next Tuesday.

Additional crews may begin work on the drainage installation required in the Barrows and Fisher yard late next week.


Construction Update Brattleboro-Hinsdale Bridge – March 15, 2024

Crews have stripped all forms for the Pier 1 footing and stem. The footing has now been backfilled with clean stone and the cofferdam sheets have been pulled. Work has begun on the cap for Pier 1 and forms are being placed. Next Tuesday, the cap rebar will be placed on top of the stem and the remainder of the week will be spent tying the cap to the stem, installing formwork, and making final adjustments to be ready for concrete. Another crew may begin work on drainage installation required in the Barrows and Fisher yard next week as well.