Construction Update
Brattleboro-Putney PS 25(11)
Brattleboro NH PC 25(5)
DATE: Friday, April 17, 2026
TRAFFIC IMPACTS:
Brattleboro-Putney STP PS 25(11)
Shoulder closures are anticipated Monday and Tuesday of next week in the northern part of the project as a part of the traffic control coordination effort with Green Mountain Power.
Beginning Wednesday, one 1.5 mile long single-lane closure will be in place on U.S. Route 5 beginning at the Interstate 91 overpass in Brattleboro and progressing north. Flaggers will assist with alternating traffic patterns through the work zone. The work zone will shift from northbound to southbound travel lanes and continue to progress north over the course of the week. Motorcyclists should watch for grooved and uneven surfaces. Expect delays in this area.
Brattleboro-Putney STP PS25(11) Fig. 1: Day work locations for U.S. 5 work.
CONSTRUCTION ACTIVITIES:
Brattleboro-Putney STP PS 25(11)
Crews will work off the shoulders on swale remediation, erosion control corrections, and turf establishment along U.S. 5 on Monday and Tuesday next week from 7:00 a.m. to 4:00 p.m. Wednesday through Friday the contractor plans to begin their milling operation (grinding the top layer of pavement off and leaving a grooved surface). They will begin in the northbound lane near the I-91 overpass and proceed for 1.5 miles, then turn around and mill the southbound lane the next day to level the road.
LOCATION:
This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.
Brattleboro PC25(5)
VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.
Brattleboro PC 25(5) Locations on VT 9.
Brattleboro-Putney STP PS25(11)
U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.
Brattleboro-Putney STP PS25(11) Fig. 2: U.S. 5 Night work locations.
Brattleboro PC25(6) – Substantially Complete in 2025
U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.
VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.
VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.
VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.
OVERALL PROJECT COMPLETION: Fall 2026