Brattleboro and Brattleboro-Putney Paving Construction Update 06/05/2026
The contractor has added an additional night shift across all evening work zones and will be working overnight Friday night into Saturday morning beginning next week on June 12, 2026.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Flaggers will control alternating traffic patterns in all intersections and through single-lane closures on Vermont Route 9 between the Interstate 91 Exit 2 interchange and the Edmund Heights intersection in West Brattleboro. Monday night through Saturday morning, work zones will be active from 7 p.m. and 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m. Monday night through Saturday morning.