Brattleboro and Brattleboro-Putney Paving Construction Update 10/09/2026

DATE: Friday, October 9, 2026

No work will be conducted on the project from Noon Friday, October 9 until crews return to work Tuesday, October 13 at 6 a.m. in observance of Indigenous Peoples’ Day.

TRAFFIC IMPACTS:

Vermont Route 9: (Night Work)

Single-lane closures with alternating traffic patterns controlled by flaggers are planned from the Exit 2 interchange to the Edward Heights intersection from 7 p.m. to 6 a.m. Monday night through Saturday morning. No street-side parking will be available through the work zone. Motorists should watch for wet paint.


Brattleboro and Brattleboro-Putney Paving Construction Update 09/25/2026

DATE: Friday, September 25, 2026

Overnight work is planned for tonight Friday, September 25, 2026 from 7 p.m. to 6 a.m.

TRAFFIC IMPACTS:

Vermont Route 9: (Night Work)

Single-lane closures with alternating traffic patterns controlled by flaggers are planned from the Exit 2 interchange to the Edward Heights intersection from 7 p.m. to 6 a.m. Monday night through Saturday morning. No street-side parking will be available through the work zone. Motorists should watch for wet paint.


Brattleboro and Brattleboro-Putney Paving Construction Update 07/31/2026

Milling and side road paving are scheduled on U.S. Route 5 in the vicinity of the Exit 3 roundabout from 7 p.m. tonight, Friday, July 31, to 6 a.m. Saturday morning, August 1.

There will be NO CLOSURE of Interstate 91, Exit 3 on- and off- ramps Saturday, August 1. Closures are scheduled for next week (see below).

Guardrail work is scheduled on Vermont Route 9 from 7 p.m. Sunday, August 2 to 6 a.m. Monday, August 3.


Brattleboro and Brattleboro-Putney Paving Weekend Work 07/29/2026

Overnight work is planned for this Friday, July 31 and Sunday, August 2.

Friday, July 31st into Saturday morning August 1st, crews will continue paving on U.S. Route 5 between Noah’s Lane and Bennett Drive. Single-lane closures will be in place and uniformed traffic officers and flaggers will direct traffic through alternating traffic patterns as needed.

The on- and off- ramps in all directions for Interstate 91 Exit 3 are planned to be closed from 12 a.m. to 5 a.m. Saturday morning, August 1st.


Brattleboro I-91 Exit 3 Short-Duration Closure Schedule 7/27/2026

Interstate 91, Exit 3 Closure Schedule

Interstate 91 Exit 3 on- and off-ramps for northbound and southbound are scheduled to be closed THIS WEEK on the following dates and times:

Tuesday, July 28, 12 a.m. – 5 a.m.

Wednesday, July 29, 12 a.m. – 5 a.m.

Thursday, July 30, 12 a.m. – 5 a.m.

Friday, July 31, 12 a.m. – 5 a.m.


Brattleboro and Brattleboro-Putney Paving Construction Update 07/24/2026

Overnight work on U.S. Route 5 and Vermont Route 9 is planned for 7 p.m. tonight Friday, July 24 to 6 a.m. Saturday morning, July 25.

TRAFFIC IMPACTS:

Interstate 91, Exit 3: Brattleboro (Night Work)

Short-duration closures of Exit 3 are planned for next week. Daily, from 12 a.m. to 5 a.m. July 28-July 31, the on- and off- ramps will be closed in both directions for Interstate 91 Exit 3. Confirmation of the schedule for these closures will be distributed on Monday, July 27.


Brattleboro and Brattleboro-Putney Paving Construction Update 07/10/2026

Vermont Route 9: (Night Work)

Between the Interstate 91 Exit 2 interchange and the Edward Heights intersection in West Brattleboro, flaggers will control alternating traffic patterns through single-lane closures on VT 9. Monday night through Friday morning, work zones will be active from 7 p.m. to 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m.

Pedestrians: Please exercise caution when navigating the work zone. Sidewalk work will continue on VT 9 through next week. Pedestrians should watch for sidewalk detours and accessible ramps.


Brattleboro and Brattleboro-Putney Paving Construction Update 06/26/2026

There will be no overnight work tonight, Friday, June 26, 2026.

Crews will be off the road at Noon on Thursday, July 2, returning to work at 6 a.m. on Monday, July 6 in observance of the Independence Day Holiday.

TRAFFIC IMPACTS:

Vermont Route 9: (Night Work)

Flaggers will control alternating traffic patterns through single-lane closures on VT 9 between the Interstate 91 Exit 2 interchange and the Edward Heights intersection in West Brattleboro. Monday night through Thursday morning, work zones will be active from 7 p.m. to 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m. Monday night through Thursday morning.