Brattleboro and Brattleboro-Putney Paving Construction Update 07/31/2026

Milling and side road paving are scheduled on U.S. Route 5 in the vicinity of the Exit 3 roundabout from 7 p.m. tonight, Friday, July 31, to 6 a.m. Saturday morning, August 1.

There will be NO CLOSURE of Interstate 91, Exit 3 on- and off- ramps Saturday, August 1. Closures are scheduled for next week (see below).

Guardrail work is scheduled on Vermont Route 9 from 7 p.m. Sunday, August 2 to 6 a.m. Monday, August 3.


Brattleboro and Brattleboro-Putney Paving Weekend Work 07/29/2026

Overnight work is planned for this Friday, July 31 and Sunday, August 2.

Friday, July 31st into Saturday morning August 1st, crews will continue paving on U.S. Route 5 between Noah’s Lane and Bennett Drive. Single-lane closures will be in place and uniformed traffic officers and flaggers will direct traffic through alternating traffic patterns as needed.

The on- and off- ramps in all directions for Interstate 91 Exit 3 are planned to be closed from 12 a.m. to 5 a.m. Saturday morning, August 1st.


Brattleboro I-91 Exit 3 Short-Duration Closure Schedule 7/27/2026

Interstate 91, Exit 3 Closure Schedule

Interstate 91 Exit 3 on- and off-ramps for northbound and southbound are scheduled to be closed THIS WEEK on the following dates and times:

Tuesday, July 28, 12 a.m. – 5 a.m.

Wednesday, July 29, 12 a.m. – 5 a.m.

Thursday, July 30, 12 a.m. – 5 a.m.

Friday, July 31, 12 a.m. – 5 a.m.


Brattleboro and Brattleboro-Putney Paving Construction Update 07/24/2026

Overnight work on U.S. Route 5 and Vermont Route 9 is planned for 7 p.m. tonight Friday, July 24 to 6 a.m. Saturday morning, July 25.

TRAFFIC IMPACTS:

Interstate 91, Exit 3: Brattleboro (Night Work)

Short-duration closures of Exit 3 are planned for next week. Daily, from 12 a.m. to 5 a.m. July 28-July 31, the on- and off- ramps will be closed in both directions for Interstate 91 Exit 3. Confirmation of the schedule for these closures will be distributed on Monday, July 27.


Brattleboro and Brattleboro-Putney Paving Construction Update 07/10/2026

Vermont Route 9: (Night Work)

Between the Interstate 91 Exit 2 interchange and the Edward Heights intersection in West Brattleboro, flaggers will control alternating traffic patterns through single-lane closures on VT 9. Monday night through Friday morning, work zones will be active from 7 p.m. to 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m.

Pedestrians: Please exercise caution when navigating the work zone. Sidewalk work will continue on VT 9 through next week. Pedestrians should watch for sidewalk detours and accessible ramps.


Brattleboro and Brattleboro-Putney Paving Construction Update 05/22/2026

DATE: Friday, May 22, 2026

No work will be conducted on the project from Noon on Friday, May 22, 2026 until 6 a.m. Tuesday, May 26, 2026 in observance of the Memorial Day Holiday.

TRAFFIC IMPACTS:

Vermont Route 9: (Night Work)

Single-lane closures are scheduled to be in place on Vermont Route 9 beginning at the Greenleaf Street intersection in West Brattleboro and progressing east to the Interstate 91 Exit 2 interchange. Between the hours of 7 p.m. and 6 a.m. Tuesday night through Friday morning, flaggers will direct alternating traffic patterns through the work zones. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m. Tuesday night through Friday morning. Motorcyclists should watch for grooved and uneven surfaces.


Brattleboro-Putney U.S. 5 Paving Construction Update 04/24/2026

Brattleboro-Putney STP PS 25(11)

An individual work zone with one single-lane closure will continue to be in place on U.S. Route 5 in Dummerston with work progressing north. Flaggers will assist with alternating traffic patterns through the work zone. The work zone will shift from the northbound to the southbound travel lanes and may lengthen over the course of a day to a maximum distance of 1.5 miles. Motorcyclists should watch for grooved and uneven surfaces. Expect delays in this area.


Brattleboro-Putney U.S. 5 Paving Construction Update 04/17/2026

TRAFFIC IMPACTS:

Brattleboro-Putney STP PS 25(11)

Shoulder closures are anticipated Monday and Tuesday of next week in the northern part of the project as a part of the traffic control coordination effort with Green Mountain Power.

Beginning Wednesday, one 1.5 mile long single-lane closure will be in place on U.S. Route 5 beginning at the Interstate 91 overpass in Brattleboro and progressing north. Flaggers will assist with alternating traffic patterns through the work zone. The work zone will shift from northbound to southbound travel lanes and continue to progress north over the course of the week. Motorcyclists should watch for grooved and uneven surfaces. Expect delays in this area.


Brattleboro-Putney U.S. 5 Paving Project Construction Update 3/25/2026

Construction is scheduled to resume on U.S. Route 5 from Brattleboro to Putney on Monday, April 6th during daytime hours.

Crews will begin to mobilize anticipating their start of work on the U.S. 5 portion of the project from north of the Interstate 91 overpass (just south of the intersection with Bennet Drive) and progressing north to Putney. Restricted shoulders and single-lane closures with alternating traffic patterns controlled by flaggers will be in place as needed.


Brattleboro VTrans Paving Project Construction Update 11/21/2025

Work is finishing up on U.S. 5 (Putney Road) from the intersection with Vermont Avenue to Noah’s Lane. Nighttime single-lane closures will be in place as needed Monday and Tuesday nights from 4:00 p.m. to 6:00 a.m. with flaggers present to direct one-way alternating traffic through the work zone.

Daytime single-lane closures are scheduled to continue next week on U.S. 5 in Dummerston progressing south Monday through Wednesday. Flaggers will direct alternating traffic patterns through the work zones.


Brattleboro VTrans Paving Project Construction Update 11/07/2025

Nighttime single-lane closures controlled by flaggers will be present as needed from Monday night through Saturday morning, 7:00 p.m. to 6:00 a.m. Work is finishing up on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Main and Canal Street), and Vermont Route 30 (Linden Street). Motorists should watch for wet paint.


Brattleboro VTrans Paving Project Construction Update 10/31/2025

The Class 1 paving project is finishing up throughout downtown. Crews are working on VT 9 (Western Avenue and High Street) and will be finishing up in areas on U.S. 5 (Canal Street and Main Street). Work to be done includes hand painting (symbols, stop bars, crosswalks, etc.), sign installation, and some signal work.


Brattleboro VTrans Paving Project Construction Update 10/24/2025

Due to the Halloween Holiday on Friday, October 31st, 2025, crews will postpone their construction start as needed to accommodate trick or treaters.

TRAFFIC IMPACTS:

Brattleboro NH PC 25(6)

Nighttime single-lane closures will be in place as needed Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. for work on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Main and Canal Street), and Vermont Route 30 (Linden Street). Flaggers will be present to direct one-way alternating traffic through the work zones. Motorists should watch for wet paint.


Brattleboro VTrans Paving Project Construction Update 10/17/2025

Between Vermont Avenue and Noah’s Lane, crews will work on bridge joints and the painting operation will move to this location after paint is complete in the downtown area.

Once this section is complete and in the next few weeks, crews plan to move the active work zone from night shift to day shift and to continue to make progress on U.S. 5 from the Brattleboro/Dummerston town line north toward Putney.