Brattleboro VTrans Paving Project Construction Update 9/19/2025

Construction Update

Brattleboro NH PC 25(6)

Brattleboro NH PC 25(5)

Brattleboro-Putney PS 25(11)

DATE: Friday, September 19, 2025

TRAFFIC IMPACTS:

Brattleboro NH PC 25(6)

Nighttime single-lane closures will be in place Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. Work will continue on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Main Street), Vermont Route 30 (Linden Street), and briefly on Vermont Route 142 (Vernon Street). Flaggers will be present to direct one-way alternating traffic through multiple work zones. Motorcyclists should watch for grooved and uneven surfaces. All motorists should be aware of raised utility structures.

Parking restrictions will be enforced during working hours. Pedestrians should watch for sidewalk detours.

Brattleboro-Putney STP PS 25(11)

Nighttime single-lane closures will be in place Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. on U.S. 5 (Putney Road) from the intersection with Vermont Avenue to the approximate intersection with Noah’s Lane. Flaggers will be present to direct one-way alternating traffic through the work zones. Motorcyclists should watch for grooved and uneven surfaces.

PARKING IMPACTS:

Street side parking will be unavailable and strictly enforced on all project routes. From 7:00 p.m. to 6:00 a.m. Monday night through Saturday morning, please pay attention to nightly message boards indicating parking restrictions. The contractor and Brattleboro DPW are working together to move these boards for locations of work each evening. To see alternative lots with rates and hours, please go to https://brattleboro.gov/parking.

Phasing and Parking Information for Brattleboro NH PC 25(6)

2025 09 18 work corridors

CONSTRUCTION ACTIVITIES:

Crews continue to measure decibel levels with noise monitoring equipment throughout the work area.

Brattleboro NH PC 25(6)

Linden Street (VT 30) – Sidewalk work and paving should be finished by the end of next week.

Vernon Street (VT 142) -Shoulder work is scheduled. Permanent pavement markings remain to be done.

Canal Street (U.S. 5) – No major work is scheduled through this corridor for next week.

Western Avenue and High Street (VT 9) – The sidewalk crew will continue to make progress on this corridor.

Main Street (U.S. 5) – Paving should finish up here next week.

Brattleboro-Putney STP PS 25(11)

The contractor is going to proceed with milling operations on part of the next phase of the project. Milling will begin on Putney Road (U.S. 5) near the intersection with Vermont Avenue and progress north over the course of the week to approximately the intersection with Noah’s Lane. If milling is completed in this area, the contractor will move on to paving the first lift of pavement through here.

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.

Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.

Brattleboro PC25(6)

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.

VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.

VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.

VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.

Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.

BRATTLEBORO NH PC25(6) INTERIM COMPLETION: Fall 2025

OVERALL PROJECT COMPLETION: Fall 2026

Contact Information:

Name – Bethany Oprendek

Phone – 802.267.4044

Email – bethany@bbo-enterprises.com