I-91 Brattleboro Bridge Replacement Project Update – 8-Week Look-Ahead

Route 30

After September 30th, the project team may need to regulate traffic flow on Route 30 periodically to allow truck or equipment access to our work zone. These operations will be controlled by flaggers and will be for a maximum of 10 minutes.

During the week of October 7th, one lane of Route 30 will be closed during the day for approximately two days. Flaggers will regulate vehicle movement through the work zone.

Looking further out, we are currently anticipating short duration closures of Route 30 due to overhead demolition activities in late November or early December. As we progress in our sequence we will let stakeholders know the dates and duration of these closures.

West River

From November 1st thru November 30th, the project team will be removing the existing Northbound I-91 Bridge spans over the West River. The team will install navigation buoy devices for recreation traffic on the West River directing them under spans that will not have overhead operations. We do not anticipate the need to close the West River to recreational users during these operations. Should there be a change in conditions and there is a need to close the West River to recreation, we will provide public notice.

Cindy Cook, Public Relations Officer, Adamant Accord, Inc. ccook@adamantaccord.com.