Brattleboro and Brattleboro-Putney Paving Construction Update 05/29/2026

Construction Update

Brattleboro-Putney PS 25(11)

Brattleboro NH PC 25(5)

Brattleboro STP PC25(6)

DATE: Friday, May 29, 2026

TRAFFIC IMPACTS:

Vermont Route 9: (Night Work)

Flaggers will control alternating traffic patterns in all intersections and through single-lane closures on Vermont Route 9 beginning at the Edmund Heights intersection in West Brattleboro and progressing east to the Interstate 91 Exit 2 interchange. Work zones will be active from 7 p.m. and 6 a.m. Monday night through Friday morning. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m.

U.S. Route 5: Brattleboro to Putney (Day Work)

Flaggers will control alternating traffic patterns and assist motorists into driveways and side streets. After side road paving is complete, a single-lane closure will be in place on U.S. Route 5 for the application of final pavement. This lane closure will lengthen over the course of the day to a maximum distance of 1.5 miles and alternate between north- and south-bound lanes. From 7 a.m. to 4:30 p.m. delays are anticipated in this area.

Downtown Brattleboro (Night Work)

A mobile work zone is scheduled from 7 p.m. to 6 a.m. throughout downtown Brattleboro. Uniformed Traffic Officers will assist and short lane closures with alternating traffic patterns may be implemented at times.

CONSTRUCTION ACTIVITIES:

Vermont Route 9: (Night Work)

Milling of side roads and driveways in anticipation of paving will begin next week. Crews will continue to adjust drainage and utility structures throughout the project limits. Note: crews will have noise monitoring equipment to measure the decibel levels of this operation.

U.S. Route 5: Brattleboro to Putney (Day Work)

Milling and paving of side roads and driveways will continue until complete. Once finished, the final pavement layer will be applied.

Downtown Brattleboro (Night Work)

The vacuum truck will continue to clean out structures. This work is nearing completion, but they anticipate a couple more weeks of this operation as the crew is available.

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.

Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.

Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.

Brattleboro PC25(6) – Substantially Complete in 2025

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.

VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.

VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.

VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.

OVERALL PROJECT COMPLETION: Fall 2026

Contact Information:

Name – Bethany Oprendek

Phone – 802.267.4044

Email – bethany@bbo-enterprises.com