Brattleboro and Brattleboro-Putney Paving Construction Update 11/13/2026
DATE: Friday, November 13, 2026
NO overnight work is scheduled for tonight,
Friday, 11/13 or Sunday, 11/15.
DATE: Friday, November 13, 2026
NO overnight work is scheduled for tonight,
Friday, 11/13 or Sunday, 11/15.
Overnight work is scheduled across all work zones for tonight, Friday, 10/16, Sunday, 10/18, and Friday, 10/23.
Shoulder and side-road pavement marking operations will begin at 4 p.m. in the afternoon starting next week.
DATE: Friday, October 9, 2026
No work will be conducted on the project from Noon Friday, October 9 until crews return to work Tuesday, October 13 at 6 a.m. in observance of Indigenous Peoples’ Day.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Single-lane closures with alternating traffic patterns controlled by flaggers are planned from the Exit 2 interchange to the Edward Heights intersection from 7 p.m. to 6 a.m. Monday night through Saturday morning. No street-side parking will be available through the work zone. Motorists should watch for wet paint.
Overnight work is planned for tonight Friday, October 2, 2026 from 7 p.m. to 6 a.m.
No work will be conducted on the project from Noon Friday, October 9 until crews return to work Tuesday, October 13 at 6 a.m. in observance of Indigenous Peoples’ Day.
DATE: Friday, September 25, 2026
Overnight work is planned for tonight Friday, September 25, 2026 from 7 p.m. to 6 a.m.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Single-lane closures with alternating traffic patterns controlled by flaggers are planned from the Exit 2 interchange to the Edward Heights intersection from 7 p.m. to 6 a.m. Monday night through Saturday morning. No street-side parking will be available through the work zone. Motorists should watch for wet paint.
The Town of Brattleboro would like to inform the public of a temporary closure of Maple Street to accommodate private utility work associated with a development project in the area.
Maple Street will be closed between the I-91 overpass and the intersection of Maple Street and Austine Drive on Monday, August 24, and Tuesday, August 25.
The anticipated schedule is as follows:
DATE: Friday, August 14, 2026
No Friday overnight work is scheduled for tonight August 14, 2026.
TRAFFIC IMPACTS:
Interstate 91, Exit 3: (Night Work)
No Exit 3 closures are planned for next week.
Interstate 91, Exit 3 Closure Schedule
Interstate 91 Exit 3 on- and off-ramps for northbound and southbound are scheduled to be closed THIS WEEK on the following dates and times:
Tuesday, August 11, 12 a.m. – 5 a.m.
Interstate 91, Exit 3 Closure Schedule
Interstate 91 Exit 3 on- and off-ramps for northbound and southbound are scheduled to be closed THIS WEEK on the following dates and times:
Tuesday, July 28, 12 a.m. – 5 a.m.
Wednesday, July 29, 12 a.m. – 5 a.m.
Thursday, July 30, 12 a.m. – 5 a.m.
Friday, July 31, 12 a.m. – 5 a.m.
Overnight work on U.S. Route 5 and Vermont Route 9 is planned for 7 p.m. tonight Friday, July 24 to 6 a.m. Saturday morning, July 25.
TRAFFIC IMPACTS:
Interstate 91, Exit 3: Brattleboro (Night Work)
Short-duration closures of Exit 3 are planned for next week. Daily, from 12 a.m. to 5 a.m. July 28-July 31, the on- and off- ramps will be closed in both directions for Interstate 91 Exit 3. Confirmation of the schedule for these closures will be distributed on Monday, July 27.
Interstate 91, Exit 3
Upcoming Closures
Interstate 91 Exit 3 on- and off-ramps are now scheduled to be closed NEXT WEEK from 12 a.m. to 5 a.m. on the following dates:
Tuesday – Friday, July 28-31
DATE: Friday, July 17, 2026
There will be no Friday night overnight work tonight, July 17.
Overnight work on U.S. Route 5 may occur next Friday, July 24 into Saturday morning, July 25.
Interstate 91 Exit 3 on- and off-ramps for northbound and southbound are scheduled to be closed THIS WEEK on the following dates and times:
Tuesday, July 14, 12 a.m. – 5 a.m.
Wednesday, July 15, 12 a.m. – 5 a.m.
Interstate 91 Exit 3 on- and off-ramps are scheduled to be closed from 12 a.m. to 5 a.m. on the following dates:
Tuesday – Friday, July 7 – 10
Tuesday – Friday, July 14 – 17
Tuesday – Friday, July 21 – 24
There will be no overnight work tonight, Friday, June 26, 2026.
Crews will be off the road at Noon on Thursday, July 2, returning to work at 6 a.m. on Monday, July 6 in observance of the Independence Day Holiday.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Flaggers will control alternating traffic patterns through single-lane closures on VT 9 between the Interstate 91 Exit 2 interchange and the Edward Heights intersection in West Brattleboro. Monday night through Thursday morning, work zones will be active from 7 p.m. to 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m. Monday night through Thursday morning.
Interstate 91 Exit 3 on- and off-ramps are scheduled to be closed from 12 a.m. to 5 a.m. on the following dates:
Tuesday – Friday, July 7 – 10
Tuesday – Friday, July 14 – 17
Tuesday – Friday, July 21 – 24
Crews will work overnight Friday, June 26 to Saturday, June 27 on U.S. Route 5 and Vermont Route 9.
Night work is scheduled for next week on U.S. 5 beginning north of the Interstate 91 overpass at the intersection with Bennett Drive to the project limits in Putney for the application of pavement markings on side roads.
The contractor has added an additional night shift across all evening work zones and will be working overnight Friday night into Saturday morning beginning next week on June 12, 2026.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Flaggers will control alternating traffic patterns in all intersections and through single-lane closures on Vermont Route 9 between the Interstate 91 Exit 2 interchange and the Edmund Heights intersection in West Brattleboro. Monday night through Saturday morning, work zones will be active from 7 p.m. and 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m. Monday night through Saturday morning.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Flaggers will control alternating traffic patterns in all intersections and through single-lane closures on Vermont Route 9 beginning at the Edmund Heights intersection in West Brattleboro and progressing east to the Interstate 91 Exit 2 interchange. Work zones will be active from 7 p.m. and 6 a.m. Monday night through Friday morning. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m.
A combative public greeted the selectboard to kick off their Tuesday night meeting. The quick version: downtown is unsafe and your website sucks.
After that was out of the way, the board was treated to a discussion of I-91 exit 1 bridge repairs next spring and summer, emergency housing plans, and about EMS transition items such as potential municipal revenue, the RFI process, and a new project-related website.