Construction Update
Brattleboro NH PC 25(6)
Brattleboro NH PC 25(5)
Brattleboro-Putney PS 25(11)
DATE: Thursday, July 3, 2025
In observance of the Independence Day Holiday, crews will be off the road at Noon on Thursday, July 3rd and return to work Monday, July 7th.
TRAFFIC IMPACTS:
Motorists should watch for crews accessing the shoulders on Vermont Route 9, Vermont Route 30, U.S. Route 5, and Vermont Route 142 as well as all approach routes and side streets while they install construction signs.
CONSTRUCTION ACTIVITIES:
Sign installation crews will continue to work on installing construction signs on all project and approach routes. They will also be conducting project layout while plans for the project finalize. This work will be done during day time working hours.
The contractor is going to begin work this season on the Brattleboro NH PC25(6) project which is throughout the Class 1 limits of VT 142, VT 9, VT 30 and U.S. 5. Please see the infographic below.
The contractor plans to begin night work on Monday, July 14th at the U.S. 5 and VT 142 intersection in town and proceed south on U.S. 5. Crews will be working 7:00 p.m. to 6:00 a.m. Monday night through Saturday morning.
LOCATION:
This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.
Brattleboro PC25(5)
VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.
Brattleboro PC25(6)
U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.
VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.
VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.
VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.
Brattleboro-Putney STP PS25(11)
U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.
BRATTLEBORO NH PC25(6) INTERIM COMPLETION: Fall 2025
OVERALL PROJECT COMPLETION: Fall 2026
Contact Information:
Name – Bethany Oprendek
Phone – 802.267.4044
Email – bethany@bbo-enterprises.com