I-91 and Exits 2 & 3 On-Ramp Closures for Blasting: Today and Weekdays for Next 3 Weeks

Blasting Today

· The first blast will be at approximately 1:30 today.

· To ensure travelers’ safety, rolling roadblocks will be implemented on I-91 in each direction, and the on-ramps at Exits 2 Northbound and 3 in both directions will be closed for approximately 15 minutes.

· Traffic attempting to use Exits 2 and 3 on-ramps will be detoured to VT Route 5.

· Sound impacts associated with the blasting will be minimal.

Future Blasting

· Blasting will occur weekdays at about 1:30-2:00 for approx. 3 weeks.

· If you would like to be notified of the timing of the blasts each day, please subscribe to the project’s text alert system by texting 313131 with the keyword “I91Brat”.

· For more information, please contact Public information Officer Cindy Cook, ccook@adamantaccord.com, 802-272-2829.

Cindy Cook
Principal, Adamant Accord, Inc.
Past Vice President, Association for Conflict Resolution