I-91 Brattleboro Bridge Replacement Project Update: Week of January 17

I-91

To reduce congestion on I-91, both Exit 3 on ramps will be closed on Monday, January 18, (Martin Luther King’s Birthday) from 11:00 am to 6:00 pm. I-91 will remain open.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 may be reduced to a single lane intermittently, with flaggers regulating traffic within the work zone.

Upper Dummerston Road

The project will not have any direct effects on Upper Dummerston Road.

West River Trail

The West River Trail is open. There are intersections between construction access and the trail path, and users should exercise extreme caution at these intersections. As an additional safety precaution, users of the West River Trail are reminded to keep pets on a leash in this area.

West River

Construction of the new bridges sections over the West River will continue through the winter.

Text Alert System

A text alert system for the Brattleboro Bridge Replacement Project makes it possible to receive text notifications of:

• Interstate ramp closings,

• Closings of I-91,

• Closings of VT Route 30 (but not single lane closings of RT 30), and

• Any other situations regarding time sensitive project-related traffic issues.

People can sign up for this service by texting 313131 with the keyword “I91Brat”, or by using the signup widget on the project website www.i91brattleborobridge.com.

Project Progress

· Casting of the segments will continue through the winter.

· Construction of the Pier Table at Pier 2 is nearing completion. The final concrete placement will be completed in January.

· Construction of the North Abutment is underway and will continue through the winter season.

· Abutment work at the new bridge over Upper Dummerston Road has begun and will continue through the winter season.

· The new roadway alignment will continue through the 2016 non-winter season.

Trail Talks

We will continue to hold monthly trail talks for the community. The next Trail Talk will be held following the winter season.

Safety

Please focus on safety when driving through the construction work zone and remember that it is now against the law for drivers to use a hand-held cell phone.

For More Information

If you would like additional information, or would like to add others to this distribution list, please contact Cindy Cook, Public Relations Officer, Adamant Accord, Inc. ccook@adamantaccord.com.

Leave a Reply