I-91 Brattleboro Bridge Replacement Project Update: Week of May 9th

Upper Dummerston Road will be closed Thursday, May 12th beginning at 5:00 AM and ending at 9:00 PM so that the project team can work on concrete deck placement. This work is weather dependent.

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 may be reduced to a single lane intermittently, with flaggers regulating traffic within the work zone.

Upper Dummerston Road

Upper Dummerston Road will be closed Thursday, May 12th beginning at 5:00 AM and ending at 9:00 PM so that the project team can work on concrete deck placement. This work is weather dependent. We will provide updates as the week progresses.

West River Trail

The West River Trail is open. There are intersections between construction access and the trail path, and users should exercise extreme caution at these intersections. As an additional safety precaution, users of the West River Trail are reminded to keep pets on a leash in this area.

West River

No impacts are anticipated.

Text Alert System

A text alert system for the Brattleboro Bridge Replacement Project makes it possible to receive text notifications of:

• Interstate ramp closings,

• Closings of I-91,

• Closings of VT Route 30 (but not single lane closings of RT 30), and

• Any other situations regarding time sensitive project-related traffic issues.

People can sign up for this service by texting 313131 with the keyword “I91Brat”, or by using the signup widget on the project website www.i91brattleborobridge.com.

Project Progress

· The Pier 1 segments are complete.

· The form traveler is currently being erected at Pier 2.

· Construction of the North Abutment/MSE wall will continue through the spring.

· Abutment work and girder erection at the new bridge over Upper Dummerston Road is complete. The deck will be completed within the time period noted above.

· The new roadway alignment and paving will continue through the summer.

Trail Talks

We will continue to hold trail talks for the community. The next Trail Talk will be held May 14th.

Safety

Please focus on safety when driving through the construction work zone and remember that it is now against the law for drivers to use a hand-held cell phone.

For More Information

If you would like additional information, or would like to add others to this distribution list, please contact Cindy Cook, Public Relations Officer, Adamant Accord, Inc. ccook@adamantaccord.com.

Cindy Cook
Principal, Adamant Accord, Inc.
Past Vice President, Association for Conflict Resolution
________________________________

PO Box 2
Adamant, VT 05640
ccook@adamantaccord.com
www.adamantaccord.com
Office: 802-223-1330
Cell: 802-272-2829
Fax: 802-229-6836

Leave a Reply