Brattleboro Paving Schedule

Starting Wednesday, September 11th, Northeast Paving (a contractor of the town) will be starting our annual capital paving project. Weather permitting, the following schedule is anticipated: 

Wednesday, September 11 

Cold planing: Fairview St. (#51 Fairview St. to Maple St.), Estey St. (Birge St. to Pleasant St.) 

Thursday, September 12 

Cold planing: Green St. (Church St. to #164 Green St.), Oak St. (Chapin St. to High St.) 

Friday, September 13 

Paving: Old Guilford Rd. (#98 – #320), 

Monday, September 16 – Wednesday, September 18 

Paving: Fairview St. (#51 Fairview St. to Maple St.), (Austine Dr. to Winter St.), Estey St. (Birge St. to Pleasant St.), Green St. (Church St. to #164 Green St.), and Oak St. (Chapin St. to High St.). 

Work is expected to happen between 7 am and 5 pm. On street parking will not be permitted during paving operations. No parking signs will be posted the afternoon prior to work on each street. 

Please anticipate traffic disruptions during these operations. 

If you have any questions, please contact Dan Tyler, Highway and Utilities Superintendent at (802) 254 – 4255 or dtyler@brattleboro.org. 

Leave a Reply