Construction Update
Brattleboro-Putney PS 25(11)
Brattleboro NH PC 25(5)
Brattleboro STP PC 25(6)
DATE: Friday, July 10, 2026
There will be no Friday night overnight work tonight, July 10.
TRAFFIC IMPACTS:
Vermont Route 9: (Night Work)
Between the Interstate 91 Exit 2 interchange and the Edward Heights intersection in West Brattleboro, flaggers will control alternating traffic patterns through single-lane closures on VT 9. Monday night through Friday morning, work zones will be active from 7 p.m. to 6 a.m. No street-side parking will be available in these areas of VT 9 from 6 p.m. to 6 a.m.
Pedestrians: Please exercise caution when navigating the work zone. Sidewalk work will continue on VT 9 through next week. Pedestrians should watch for sidewalk detours and accessible ramps.
U.S. Route 5: Brattleboro to Putney (Day and Night Work)
Single-lane closures will be in place on U.S. 5 between the I-91 overpass near the intersection with Bennett Drive to the project limits in Putney. From 7 a.m. to 6 p.m. Monday through Friday, flaggers will control alternating traffic patterns through the work zones.
From 7 p.m. to 6 a.m. Monday night through Friday morning, single-lane closures will be in place on side roads from Brattleboro to Putney for the application of permanent pavement markings. Flaggers and uniformed traffic officers will assist traffic through the work zones. Motorists are advised to watch for wet paint.
U.S. Route 5: Brattleboro (Night Work)
Single-lane closures will be in place on U.S. 5 from the intersection with Noah’s Lane through the Exit 3 roundabout to the intersection with Old Ferry Road. From 7 p.m. to 6 a.m. Monday night through Friday morning, flaggers and uniformed traffic officers will assist traffic through the work zone – directing alternating traffic patterns as needed. Motorcyclists should watch for grooved and uneven surfaces.
Interstate 91, Exit 3: Brattleboro (Night Work)
Planned short-duration closures are scheduled for Exit 3 Tuesday through Friday mornings, July 14 – 17, from 12 a.m. to 5 a.m. Detour routes and message boards will be posted.
CONSTRUCTION ACTIVITIES:
Vermont Route 9: (Night Work)
Sidewalk installation continues VT 9.
U.S. Route 5: Brattleboro to Putney (Day and Night Work)
Shoulder work is finishing up and may continue into next week. The application of pavement markings on side roads will continue to be placed at night.
U.S. Route 5: Brattleboro (Night Work)
Paving operations are scheduled for U.S. 5 for next week from Noah’s Lane through the Exit 3 roundabout and up to the Old Ferry Road intersection.
Interstate 91, Exit 3 Upcoming Closures: Brattleboro (Night Work)
Multiple, short-duration closures of Exit 3 are planned for next week for paving operations. From 12 a.m. to 5 a.m., Tuesday through Friday mornings July 14-17, the Exit 3 on- and off-ramps for both directions will be closed. Confirmation of the closure schedule and detour routes will be sent on Monday afternoon, July 13.
LOCATION:
This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.
Brattleboro PC25(5)
VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.
Brattleboro-Putney STP PS25(11)
U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.
Brattleboro PC25(6) – Substantially Complete in 2025
U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.
VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.
VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.
VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.
OVERALL PROJECT COMPLETION: Fall 2026
Contact Information:
Name – Bethany Oprendek
Phone – 802.267.4044
Email – bethany@bbo-enterprises.com