Brattleboro and Brattleboro-Putney Paving Weekend Work 07/29/2026

Construction Update

Brattleboro-Putney PS 25(11)

Brattleboro NH PC 25(5)

Brattleboro STP PC 25(6)

DATE: Wednesday, July 29, 2026

Overnight work is planned for this Friday, July 31 and Sunday, August 2.

Friday, July 31st into Saturday morning August 1st, crews will continue paving on U.S. Route 5 between Noah’s Lane and Bennett Drive. Single-lane closures will be in place and uniformed traffic officers and flaggers will direct traffic through alternating traffic patterns as needed.

The on- and off- ramps in all directions for Interstate 91 Exit 3 are planned to be closed from 12 a.m. to 5 a.m. Saturday morning, August 1st.

Sunday, August 2nd into Monday morning August 3rd, guardrail work is planned for Vermont Route 9 between the I-91 Exit 2 interchange and Edward Heights intersection in West Brattleboro. This crew will work off the shoulder as much as possible with uniformed traffic officers providing a follow-along vehicle. Flagger controlled single-lane closures through the work zone will be in place as needed.

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.

Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.

Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.

Brattleboro PC25(6) – Substantially Complete in 2025

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.

VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.

VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.

VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.

OVERALL PROJECT COMPLETION: Fall 2026

Contact Information:

Name – Bethany Oprendek

Phone – 802.267.4044

Email – bethany@bbo-enterprises.com