Construction Update
Brattleboro-Putney PS 25(11)
Brattleboro NH PC 25(5)
Brattleboro STP PC 25(6)
DATE: Friday, November 13, 2026
NO overnight work is scheduled for tonight,
Friday, 11/13 or Sunday, 11/15.
TRAFFIC IMPACTS:
U.S. Route 5: Brattleboro-Putney (Day work)
Single-lane closures will be in place on U.S. 5 on the bridge over Interstate 91 between Bennett Drive and Old Ferry Road from 7 a.m. to 3:30 p.m. Monday through Friday. Flaggers and uniformed traffic officers will control alternating traffic patterns through the work zone. Delays are anticipated through the work zone and motorists should watch for wet paint.
U.S. Route 5, Vermont Route 9, and Downtown Brattleboro (Night work)
Mobile work zones and single-lane closures will be in place as needed from 7 p.m. to 6 a.m. Monday night through Friday morning throughout the West Brattleboro project limits, the U.S. 5 project limits from Noah’s Lane to Old Ferry Road, and on the Class 1 limits of VT 9, U.S. 5, Vermont Route 30, and Vermont Route 142. Motorists should remain vigilant through the work zones.
CONSTRUCTION ACTIVITIES:
U.S. Route 5: Brattleboro-Putney (Day Work)
Crews are continuing to work on the I-91 overpass between Old Ferry Road and Bennett Drive. Pavement operations are complete and bridge joint work and final paint are scheduled for next week.
U.S. Route 5, Vermont Route 9, and Downtown Brattleboro
Due to the weather and holiday this week, the paint crews are finishing touch-up paint throughout the entire project limits next week.
LOCATION:
This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.
Brattleboro PC25(5)
VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.
Brattleboro-Putney STP PS25(11)
U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.
Brattleboro PC25(6) – Substantially Complete in 2025
U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.
VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.
VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.
VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.
OVERALL PROJECT COMPLETION: Fall 2026