Brattleboro and Brattleboro-Putney Paving Construction Update 11/20/2026

Construction Update

Brattleboro-Putney PS 25(11)

Brattleboro NH PC 25(5)

Brattleboro STP PC 25(6)

DATE: Friday, November 20, 2026

TRAFFIC IMPACTS:

U.S. Route 5: Brattleboro-Putney (Day work)

Short-duration, single-lane closures will be in place on U.S. 5 from Vermont Avenue through the project limits in Putney on Monday and Tuesday next week. Flaggers and uniformed traffic officers will control alternating traffic patterns as needed through pop-up work zones anticipated to be in place for less than an hour at a time. Brief delays may be encountered from 7:30 a.m. to 3:30 p.m.

Finishing up work items throughout the project limits.

CONSTRUCTION ACTIVITIES:

U.S. Route 5: Brattleboro-Putney (Day Work)

Crews anticipate addressing a few items throughout the project limits Monday and Tuesday next week, weather permitting. Where work cannot be accomplished from the shoulder, single-lane closures will be in place from Vermont Avenue to Bennett Drive. Work includes some improvements to bridge joints and manholes. From Bennett Drive north to Exit 4, crews will be dressing up the shoulders and ditch lines. Single-lane closures and delays will be the longest through this area.

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating “State Highway Ends” and “State Highway Begins”. Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.

Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.

Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.

Brattleboro PC25(6) – Substantially Complete in 2025

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.

VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.

VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.

VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.

OVERALL PROJECT COMPLETION: Fall 2026