I-91 Brattleboro Bridge Replacement Project Update: Week of August 2
Blasting operations on the north side of the new bridge will begin on August 6th or 7th. Roughly 15 separate 10-minute blasts will be needed to complete the work. The blasting will be conducted on weekdays for approximately 3 weeks; the target time for the blasts is between 1:30-2:00 pm. The contractor will need 5 minutes to verify clear lanes of travel. To ensure travelers’ safety, rolling roadblocks will be implemented on I91 in each direction. Sound impacts associated with the blasting will be minimal. More details to follow.
I-91
See above re blasting scheduled to start on August 6th or 7th.