Construction Update Brattleboro-Hinsdale Bridge – July 13

Construction Update

Brattleboro-Hinsdale

BF A004(152)

DATE: Thursday, July 13, 2023

TRAFFIC IMPACT: Vermont Route 142 remains closed from the intersection with Royal Road north to the access to 28 Vernon Street until the end of August. Separate signed detours for cars and trucks are active. Flaggers may be deployed if the volume of construction traffic necessitates their use.

Moment slab preparatory work.

Environmental controls adjacent to the river in place.

CONSTRUCTION ACTIVITIES: The Vermont side of the construction site held up well during the rain event this past Monday. Work was able to continue on the waterline, drainage, and embankment installations along the VT 142 corridor and these operations are scheduled to continue into next week.

In addition, fine grading operations have begun and will continue for the placement of northern MSE wall moment slabs. Once grading is complete; waterproof membrane, formwork, and reinforcing steel can all be installed for the 30 foot slabs.

Over the Connecticut River, the work on the bridge has paused while the contractor works to remove debris from where it has been caught by the trestle. Additionally, road closures have delayed any further delivery of steel girders to the site at this time.

DETOUR INFORMATION: The truck detour route from VT 142 will be up Cotton Mill Hill Road, left onto South Main Street, continuing onto Fairground Road, and finally back Canal Street. Cars detouring from VT 142 should proceed up Cotton Mill Hill Rd. and make a right hand turn onto South Main St. A turnaround has been constructed south of Cotton Mill Hill Rd. on VT 142 to allow vehicles to safely navigate this corridor. A three-way stop configuration has been implemented at the Cotton Mill Hill Rd. and VT 142 intersection.

LOCATION:

The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.

PROJECTED COMPLETION: Fall 2024.

Contact Information:
Name – Bethany Oprendek
Phone – 802.267.4044
Email – bethany@bbo-enterprises.com

Leave a Reply