I-91 Brattleboro Bridge Replacement Project Update: Week of April 12
I-91
On Tuesday, April 21, there will be a formal inspection of the I-91 Bridge. Daylight is needed for the inspection, so the bridge will be closed from approximately 8:00 AM to 5:00 PM. At the same time, the PCL team will repair potholes that developed over the winter. I-91 will be closed between Exits 2 and 3 both northbound and southbound. Traffic will be detoured onto VT Route 5.
Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.