I-91 Brattleboro Bridge Replacement Project Update – Week of December 1, 2013

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge in the Fall of 2015.

Night work will resume on Monday, December 2nd, and will continue Sunday through Thursday, and occasionally Friday, nights for the next several months, until demolition is complete.


I-91 Brattleboro Bridge Replacement Project Update – Week of November 24, 2013

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge in the Fall of 2015.

There will be no night work the week of November 24th. Night work will resume the week of December 2nd, and will continue Sunday through Thursday nights for the next several months, until demolition is complete.


I-91 Brattleboro Bridge Replacement Project Update – Week of November 17, 2013

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge in the Fall of 2015.

Night work on the existing I-91 bridge will begin on Sunday night, November 17th and will continue through Friday morning, November 22nd. Night work will continue Sunday through Thursday nights for the next several months, until demolition is complete.


I-91 Brattleboro Bridge Replacement Project Update – Week of November 10, 2013

I-91

Northbound I-91 traffic will be relocated onto the southbound bridge on Tuesday, November 12th. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge in the Fall of 2015.

Night work on the existing I-91bridge will begin on Tuesday night, November 12th and will continue for the next several months, until demolition is complete.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph.


Work on 1-91 Bridge Replacement in Brattleboro Leads to I-91 Lane Closures for Next Two Years

MONTPELIER, Vt.—November 8, 2013–

Work is beginning in earnest on a project to replace two existing bridges on I-91 with a single, four-lane structure that will accommodate both northbound and southbound traffic.

The PCL+FIGG Team that is working under contract to the Vermont Agency of Transportation announced today that northbound I-91 traffic will be relocated to one of the lanes on the southbound bridge starting on Tuesday, November 12th and continuing until the existing northbound bridge is demolished. Once the northbound bridge is demolished and the new bridge has been constructed, traffic will be rerouted to the new bridge while the southbound bridge is demolished. Throughout this process, traffic will be reduced to a single lane in each direction on I-91 until completion of the project in the Fall of 2015.


Brattleboro Skatepark Site Selection Committee Applications Due Nov. 14

The Town of Brattleboro is looking for citizens to serve on the newly formed Skatepark Site Selection Committee. The Committee was formed by the Selectboard on November 5, 2013, and will consist of seven interested citizens. The Recreation & Parks Director will serve as lead staff member to support the Committee and also engage staff from other Town departments as needed.


Washington Street Closed for Three Weeks

Washington Street will be closed to through traffic from Highland Street to Prospect Street for three weeks starting Monday, October 28, 2013. Renaud Bros. will be working with the Department of Public Works to replace the failed retaining wall. Motorists should plan to use alternate routes.

If there are questions or concerns, please contact the Department of Public Works at 254-4255.

-Department of Public Works


Upcoming Windham Regional Plan Public Forums: We’ve Got Questions

The Windham Regional Commission (WRC) is approximately halfway through the two-year update process for the 2014 Windham Regional Plan. The Plan reflects shared values and concerns of the people who live in the 27-towns and discusses current and future issues facing the Region. The Windham Region consists of the 23 towns of Windham County, Readsboro, Searsburg and Winhall in Bennington County, and Weston in Windsor County. The Windham Regional Plan is updated on an eight year cycle during which the information and statistics presented in the Plan, the Plan text which describes both historical and developing trends and values, and the resulting Plan policies will be reviewed and updated based on current information and conditions.


I-91 Brattleboro Bridge Replacement Project Update – Week of October 20, 2013

I-91

Single lane closure of the passing lanes on I-91 Northbound and Southbound will continue for the week of October 20. The lanes will remain closed over the weekend.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through August 2016. Truck activity on Route 30 will continue for the week of October 20. Route 30 will be reduced to a single lane intermittently. Flaggers will regulate traffic flow.


Smart Zone Tools Will Provide Public with Real Time Information re Travel Conditions for 1-91 Bridge Replacement in Brattleboro

MONTPELIER, Vt.—October 14, 2013–

The PCL+FIGG Team that is working under contract to the Vermont Agency of Transportation to reconstruct I-91 bridges in Brattleboro is using a full array of “Smart Zone” tools, including Portable Changeable Message Signs (PCMS), Wavetronics radar traffic sensors, and video cameras that will broadcast live data to a public website devoted to the project. The site’s traffic sensors will continuously monitor traffic volumes in the work zone. This information will be used to automatically post messages on project signs regarding potential delays and expected travel times.


Interstate Lanes Associated with I-91 Bridge Reconstruction to be Reopened for Columbus Day Weekend

MONTPELIER, Vt.—October 11, 2013–The Vermont Agency of Transportation (VTrans) will remove the temporary lane closures on Interstate 91 in Brattleboro over Columbus Day weekend to accommodate holiday traffic. The temporary closures are associated with construction to replace the interstate bridges between exits 2 and 3.

The northbound passing lane that is currently closed will be opened for the weekend starting at approximately 1:00 PM Friday, and the southbound passing lane will be opened at approximately 5:00 PM Friday. The northbound lane closures will go back in effect on Monday morning and the southbound lane closures will be re-established Tuesday morning.


I-91 Brattleboro Bridge Replacement Project Update – Week of October 13, 2013

I-91

Single lane closure of the passing lanes on I-91 Northbound and Southbound will continue for the week of October 13. The lanes will remain closed over the weekend.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through August 2016. Truck activity on Route 30 will continue for the week of October 13. On Wednesday, October 16 and Thursday, October 17, Route 30 will be reduced to a single lane. Flaggers will regulate traffic flow.


I-91 Brattleboro Bridge Replacement Project Update – Week of October 6, 2013

I-91

Single lane closure of the passing lanes on I-91 Northbound and Southbound will continue thru the week of October 6.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through August 2016. Truck activity on Route 30 will continue for the week of October 6. On Monday, October 7 and Tuesday, October 8, Route 30 will be reduced to a single lane. Flaggers will regulate traffic flow.


I-91 Brattleboro Bridge Replacement Project Update – Week of September 30, 2013

I-91

Single lane closure of the passing lanes on I-91 Northbound and Southbound will be in effect next week during the construction of the temporary cross-overs. The lanes will be opened over the weekend when no workers are present.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through August 2016. Truck activity on Route 30 will increase next week and shoulders will be closed. Flaggers will regulate traffic flow to allow truck and equipment access to the work zone. Traffic will be stopped for a maximum of ten minutes.


Plans Move Forward for Replacement of Melrose Terrace Senior Housing

[BRATTLEBORO, VT]: The Brattleboro Housing Authority (BHA), at a meeting today with officials from the Department of Housing and Urban Development (HUD) and representatives of Vermont’s Congressional delegation, described substantial progress in creating new affordable apartments to replace the senior public housing at Melrose Terrace damaged by Tropical Storm Irene.

“With the help of Housing Vermont, our development partner, we’re well into the predevelopment phase,” said BHA Executive Director Chris Hart.

Housing Vermont secured an option on the 2.8-acre site at 464 Canal Street in July.


I-91 Brattleboro Bridge Replacement Project Update – 8-Week Look-Ahead

Route 30

After September 30th, the project team may need to regulate traffic flow on Route 30 periodically to allow truck or equipment access to our work zone. These operations will be controlled by flaggers and will be for a maximum of 10 minutes.

During the week of October 7th, one lane of Route 30 will be closed during the day for approximately two days. Flaggers will regulate vehicle movement through the work zone.

Looking further out, we are currently anticipating short duration closures of Route 30 due to overhead demolition activities in late November or early December. As we progress in our sequence we will let stakeholders know the dates and duration of these closures.


I-91 Brattleboro Bridge Replacement Project Update – Week of September 22, 2013

I-91

Single lane closure of the passing lane on I-91 Northbound and Southbound may begin on 9/26/13. The lane closures will remain in effect during the construction of the temporary cross-overs, but will be removed over the weekend when no workers are present.

Route 30

Speed reduction on Route 30 will be implemented lowering the speed limit through the work zone to 40 mph. The reduced speed limit will remain in effect until approximately August, 2016.

Truck activity at Route 30 will be increasing next week. Expect shoulder closures beginning Thursday 9/26. Flaggers may have to halt traffic at times to allow trucks to enter and exit the work zone.


I-91 Brattleboro Bridge Replacement Project Update

We’re going to begin publishing the I-91 Bridge Replacement Project updates here each week. They come from Cindy Cooke, who is acting as Public Relations Officer for the project.

Week of September 15, 2013

I-91 – On Thursday, September 19th and Friday, September 20th , there will short duration lane closures on I-91 Northbound and I-91 Southbound while work zone signs are installed.

Route 30 – No impacts anticipated for the week of September 15.

Upper Dummerston Road – No impacts anticipated for the week of September 15.


Community Meeting on Revitalizing Brattleboro’s Downtown

The public is invited to take part in a town hall meeting on revitalizing Brattleboro’s downtown. The meeting will take place on Monday, September 9th at 5 p.m. at the Latchis Theater.

Because of the hardships downtown Brattleboro suffered as a result of Tropical Storm Irene, the State of Vermont has chosen Brattleboro, along with six other towns, to receive consulting assistance through a federal Disaster Relief Grant. As the designated downtown organization, Building a Better Brattleboro has been asked to help implement the project.


Harmony Lot Tunnel Will Be Closing

The Town of Brattleboro has been notified by representatives of Bread Loaf Construction, working on behalf of Mesabi Inc, that the Harmony Lot underpass will be closed to public access on August 6, 2013 at 6:00am. The closing is necessary to maintain public safety during the yearlong redevelopment of the Brooks House. It is anticipated that the underpass will be closed for the duration of the project.

Jan Anderson
Executive Secretary
Brattleboro Town Manager’s Office
(802) 251-8100