Brattleboro Bridge Replacement Project Update: Week of December 7
NOTE: Upcoming night closure of I-91 Northbound to re-address pothole problems. This work is weather dependent. It is tentatively scheduled for Wednesday night, December 10th between 8:00 pm and 6:00 am. The actual closure date will be communicated to stakeholders at least 48 hours in advance, after the team is able to confirm forecasted weather conditions are acceptable for work to proceed.
I-91
Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.