Construction Update Brattleboro-Hinsdale Bridge – Aug 31, 2023
The VT 142 paving operation is underway today and tomorrow, with 5″ of pavement being placed. Final pavement will be held until the entire project is closer to completion next year. Next week, placement of the bridge rail and fencing along the northern part of the project is scheduled for Tuesday, September 5th. Temporary barrier will be placed along the southern portion of the project. Temporary pavement markings are scheduled for placement on Thursday, September 7th.
VT 142 is scheduled to be opened by the end of the day Friday, September 8th. Detour signs will be taken down and/or covered as a part of the road opening process.