Construction Update Brattleboro-Hinsdale Bridge
The contractor has completed covering the retaining wall on the west side of VT 142. On the east side of VT 142, work on the mechanically stabilized earth (MSE) wall is ongoing with the placement of leveling pads. Panels and panel straps may begin to be placed later in the week. Excavation for the gravel wetland has also begun.
Pile driving operations will continue at Pier 2 next week with intermittent pounding of the diesel pile hammer anticipated from 7 AM – 7 PM.