Brattleboro Vtrans Paving Project Construction Update 8/22/2025
In observance of the Labor Day Holiday, no work will be conducted on the project after 6:00 a.m. Friday, August 29th until Tuesday, September 2nd at 7:00 p.m.
TRAFFIC IMPACTS:
Nighttime single-lane closures will be in place next week on Monday night through Friday morning from 7:00 p.m. to 6:00 a.m. Work will continue on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Canal Street and Main Street), and Vermont Route 30 (Linden Street). Flaggers will be present to direct one-way alternating traffic through multiple work zones. Motorcyclists should watch for grooved and uneven surfaces. All motorists should be aware of raised utility structures and wet paint.