Construction Update Brattleboro-Hinsdale Bridge August 17, 2023
The storm water drainage system has been completely installed along the VT 142 corridor. The video inspection of the drainage system is currently in progress with positive results to date. Pending the positive conclusion of the video inspection, the only remaining work on the drainage system will be the full clean out of the system and vertical adjustment of the frames and grates of the structures to meet the final grade of the road.
Work for the traffic signal at the new intersection where Vermont/New Hampshire Route 119 and VT 142 meet has begun with the installation of the conduit and placement of foundations for signal poles and masts. Fiber optic vaults have been set and they will continue to work on installation of ground conduit between the vaults that will run through the Vermont Abutment to New Hampshire. Installation of pedestals for the meters and controller cabinet will take place next week.