I-91 Northbound Brattleboro Bridge Closure On Saturday, April 12, 2014 – Details
BRATTLEBORO, VT – April 14 – PCL Civil Constructors, Inc., in coordination with the Vermont Agency of Transportation, closed the I-91 bridge on Saturday, April 12 through Sunday, April 13 due to unexpected safety concerns. During the demolition of the I-91 northbound bridge, safety concerns were raised when the northbound bridge shifted during the removal of a portion of the structure. As a result, the contractor recommended that, in an abundance of caution, the adjacent I-91 southbound bridge structure be closed to traffic until the partially demolished northbound bridge could be inspected and adjustments could be made to ensure the safety of the traveling public. Contractor crews and engineers worked around the clock to rectify the situation and traffic was restored Sunday night.