Construction Update Brattleboro-Hinsdale Bridge – March 7, 2024
The placement of 105 CY of concrete for the Pier 1 stem was accomplished efficiently yesterday and is now in its cure period. Crews are continuing work on the Pier 1 cap and will begin stripping the footing forms and conducting clean up of the Barrows and Fisher site. An additional crew is back at the VT Abutment site to make improvements to the bearing seats prior to structural steel placement. The pedestals will need to be brought up in elevation approximately 1.5″ so they will be chipped out and re-cast cleanly.
Next week, if early strength tests are adequate, work will begin on placing the Pier 1 cap steel and forms atop the stem, stripping stem formwork, possibly backfilling the footing, and removing the cofferdam sheets.