Construction Update Brattleboro-Hinsdale Bridge – Jan 4, 2024
The contractor has begun to advance structural steel across Pier 2 to the temporary shoring towers. This work will continue into next week. De-watering at Pier 1 site encountered several challenges last week and additional work has taken place to remediate the situation this week. The saturated conditions of the site and soil conditions have necessitated that the cofferdam be tighter in order to allow less water infiltration so the de-watering system will not be overwhelmed by the volume. The contractor has installed vertical forms at all four corners of the cofferdam and anticipates placing concrete today in order to achieve a better seal. The contractor will attempt de-watering again next week once the concrete has set up. Once a dry excavation can be maintained, the contractor will begin to install the 80 foot rebar cages in the 9 pier piles which may begin as early as next week. Footing formwork and re-bar installation may begin next week as well, overlapping with the pile operations.