Construction Update Brattleboro-Hinsdale Bridge November 9, 2023
Crews are making good progress driving the 30″ diameter steel pipes to bedrock to serve as the foundation of Pier 1. Nine are to be driven, and it is hoped they will be completed this week. If not, it will continue until completion next week.
Because of the noise, pile driving is only authorized from 7 a.m. to 7 p.m. Monday through Saturday. Once the ninth pile for Pier 1 is driven to bedrock there will be no more pile driving for this project.
The pile driving frames and platform will be removed next week, and preparations will begin for the arrival of a drill rig the following week. The drill rig will clean out the top 80 feet of each pile so they can be reinforced with concrete and reinforcing steel (rebar).