I-91 Brattleboro Bridge Replacement Project Update – Week of December 15, 2013 – Rt 30 Closure Info
I-91
Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge in the Fall of 2015.
This week, night work will be conducted Sunday through Friday nights (December 15th – 20th), and will continue Sunday through Thursday, and occasionally Friday, nights for the next several months, until demolition is complete.
Route 30
The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through the Fall of 2015.