Construction Update Brattleboro-Hinsdale Bridge – February 8, 2024
The Pier 1 cofferdam has maintained a de-watered state with manageable flows. The pipe piles have been cut to grade with steel reinforcement and concrete placed. The top of the concrete tremie is currently being cleaned to prepare for footing forms and rebar. Forms should begin to be placed today and tomorrow with rebar placed and tied beginning next week. Welding of studs is expected to be complete by this week’s end. The first concrete placement for the footing is scheduled for Tuesday, February 20th.